Water Injection Pump
Station Facilities




Expansion of existing Water Injection Pump Stations at Uthmaniyah and Haradh, For SAUDI ARAMCO under SNC LAVLIN & SAIPEM Joint Venture. As part of Saudi Aramco's Khurais program.

image01

Isuzu Knock-Down Factory


The Factory is planned to produce 600 medium duty trucks a year and in future Isuzu plans to boost the plant's annual production to 25,000 units inlcluding light and heavy duty trucks.

image01

Ma'aden Phosphate Plant


Ma'aden Phosphate Plant has awarded this contract to "Mohammad Al-Mojil Group" which in turn has requested ETE to perform the complete work on back to back to basics.

image01

Arar Substation


A SECO project, of 'Eastern Operating Area' Al Oasis has participated as main contractor where as our scope is included but not limited to complete Civil and Mechanical side.

image01

Jubail Substation


Construction of Substations 230 Kv & 115 Kv, GIS Buildings and 34.5 Kv Switchgear building, control building and complete civil, small power and mechanical works and site development works.

image01

Jeddah Stormwater
Drainage Project (JSDP)



This Mega project was conceived to control and direct the stormwater towards the sea. The whole project consists of 8 packages with 5 Dams and 3 Channels/Drainage and outfalls.

image01

Karan Gas Facilities


ETE takes pride to be a part of this project as a Subcontractor to HDEC to construct the TRAIN Substations, PIB's (Process Interface Building), Communication & Sunshade Buildings, Analyser & Car parking shelter, OME Bldg, Musalla Building snd Smoking Shelter & Civil works for pipe racks and miscellaneous foundation.

image01

Manifa Core Hydrocarbon
Facilities


Saudi ARAMCO has awarded Snamprogetti the 'Lump Sum Turnkey' project for package No-1 of Manifa Core Hydrocarbon Facilities, in the frame of Manifa Field Development program to increase the production capacity of the Kingdom of Saudi Arabia, by 900,000 barrels per day. Manifa is located 200 km north of Dhahran City, Saudi Arabia.

image01

Projects

FUTURE CERAMIC

COMPLETE ELECTRO-MECHANICAL WORKS OF CERAMIC & PORCELAIN FACTORY

?

Along with the construction of Future ceramic factory, the client has awarded ETE the remaining complete works of 'Electro-Mechanical' on pure performance and satisfaction basis.

?

KEY FEATURES OF THE PROJECT

?

? Supply, installation, testing and commissioning of MV switch-gears, power transformers, ATS, MDBs, panel boards, power factor correction units etc.

? Supply and installation of all underground and above ground cables, cable trays, conduits, MV, LV cables, wiring, lighting etc

? Supply, Installation, Termination, Testing and Commissioning of low current works like CCTV, PA/GA system, Access Control, Fire Alarm and detection system

? Telecommunication works

? Supply and installation of all kind of pumps, such domestic water pumps, submersible pumps, Fire water pumps etc

? All works related to supply and installation of fire fighting network, gas network, compressed network, water distribution network, sewer and drainage network etc.

? Equipments such as compressors, exhaust fans, ACCUs and AHUs, etc

? HVAC equipment, Ducting and Accessories

? Termination of all the equipments and instruments for entire factory

? Structural steel supports for equipments

?

PROJECT'S TITLE :?

CONSTRUCTION OF ELECTRO-MECHANICAL WORKS OF FUTURE CERAMIC FACTORY

?

CLIENT :?

FUTURE CERAMIC

?

TIME FRAME :?

JANUARY 27, 2009 - JULY 27, 2009

?

LOCATION OF PROJECT :?

2ND INDUSTRIAL ESTATE, DAMMAM, K.S.A.