Water Injection Pump
Station Facilities




Expansion of existing Water Injection Pump Stations at Uthmaniyah and Haradh, For SAUDI ARAMCO under SNC LAVLIN & SAIPEM Joint Venture. As part of Saudi Aramco's Khurais program.

image01

Isuzu Knock-Down Factory


The Factory is planned to produce 600 medium duty trucks a year and in future Isuzu plans to boost the plant's annual production to 25,000 units inlcluding light and heavy duty trucks.

image01

Ma'aden Phosphate Plant


Ma'aden Phosphate Plant has awarded this contract to "Mohammad Al-Mojil Group" which in turn has requested ETE to perform the complete work on back to back to basics.

image01

Arar Substation


A SECO project, of 'Eastern Operating Area' Al Oasis has participated as main contractor where as our scope is included but not limited to complete Civil and Mechanical side.

image01

Jubail Substation


Construction of Substations 230 Kv & 115 Kv, GIS Buildings and 34.5 Kv Switchgear building, control building and complete civil, small power and mechanical works and site development works.

image01

Jeddah Stormwater
Drainage Project (JSDP)



This Mega project was conceived to control and direct the stormwater towards the sea. The whole project consists of 8 packages with 5 Dams and 3 Channels/Drainage and outfalls.

image01

Karan Gas Facilities


ETE takes pride to be a part of this project as a Subcontractor to HDEC to construct the TRAIN Substations, PIB's (Process Interface Building), Communication & Sunshade Buildings, Analyser & Car parking shelter, OME Bldg, Musalla Building snd Smoking Shelter & Civil works for pipe racks and miscellaneous foundation.

image01

Manifa Core Hydrocarbon
Facilities


Saudi ARAMCO has awarded Snamprogetti the 'Lump Sum Turnkey' project for package No-1 of Manifa Core Hydrocarbon Facilities, in the frame of Manifa Field Development program to increase the production capacity of the Kingdom of Saudi Arabia, by 900,000 barrels per day. Manifa is located 200 km north of Dhahran City, Saudi Arabia.

image01

Projects

ARAR SUBSTATION

CONSTRUCTION OF 132/13.8 KV SUBSTATION

A SECO project, of 'Eastern Operating Area' Al Osais has participated as main contractor where as our scope is included but not limited to complete Civil and Mechanical side.

KEY FEATURES OF THE PROJECT

Construction of ARAR 132 / 13.8 kv Substation and associated works.

Site Development

Precast boundary wall and cast in site retaining wall construction

Asphalting area

Construction of substation building with basement GIS building and all finishing works

Construction of control room and its associated finishing works

Equipment foundations for ACCU, Manholes, Hand Holes, Gantry foundation including piling works

Power Transformer foundation, station service transformer foundations, septic tank etc.

All Civil, plumbing, electrical and structural work related with the substation.

PROJECT'S TITLE :

CONSTRUCTION OF 132 / 13.8 KV SUBSTATION

CLIENT :

SAUDI ELECTRIC COMPANY / AL OSAIS CONTRACTING CO.

TIME FRAME :

JANUARY 29, 2009 - NOVEMBER 29 2009

LOCATION OF PROJECT :

ARAR, K.S.A.